26 Intel
®
Modular Server System Service Guide
Installing and Removing a Storage Control Module
The Intel
®
Modular Server System MFSYS25/MFSYS35 ships with one storage control
module pre-installed. Optionally, a second storage control module may be installed in the
open storage control module bay. A Storage Control module can only be installed in a
module bay that is designed to support that device type. The farthest bay on the left and
the farthest bay on the right are dedicated to the Storage Control Modules and are labeled
SCM. For the exact location of the storage control module bay, see Figure 5.
The Storage Control module may be removed and installed using the steps detailed in the
following sections:
• “Installing a Storage Control Module” on page 26
• “Removing a Storage Control Module” on page 27
Installing a Storage Control Module
To install a storage control module, follow these steps:
1. Review the safety and ESD information at the beginning of this manual and in the
appendices.
2. Locate an available storage control module bay and remove any installed module or
filler panel.
3. Release and rotate the module retention lever out and away from the storage control
module (see letter “A” in Figure 14).
4. Slide the storage control module into the selected module bay (see letter “B” in
Figure 14) until the bottom of the retention lever engages with the module bay.