SECTION 3 - MACHINE CONTROLS, INDICATORS, AND MACHINE OPERATION
3-38 31217162
3.17 TOWING
It is not recommended that this machine be towed except in the
event of an emergency, such as a machine malfunction or a total
machine power failure. Refer Section 4.3 for emergency towing
procedures.
3.18 PLATFORM RAILS FOLD-DOWN PROCEDURE
ONLY FOLD DOWN THE RAILS WHEN THE MACHINE IS IN THE STOWED POSITION. DO
NOT RAISE THE PLATFORM WITH THE RAILS FOLDED DOWN. THE RAILS MUST BE IN
THE UPRIGHT POSITION AND PROPERLY PINNED WHEN RAISING THE PLATFORM.
AFTER THE RAILS HAVE BEEN FOLDED DOWN, USE EXTREME CAUTION WHEN EXITING
AND ENTERING THE PLATFORM. ENTER AND EXIT PLATFORM ONLY AT THE GATE AREA
AND LADDER PROVIDED.
IF DRIVING MACHINE WITH THE PLATFORM CONTROL STATION FROM GROUND, DO
NOT HANG THE CONTROL BOX ON ANY PART OF THE MACHINE WHILE DRIVING. HOLD
THE CONTROL BOX AND KEEP AT LEAST 3 FT (1 M) DISTANCE FROM MACHINE.
1. Remove the platform control station from the rails and place
on the platform floor.
2. Lift up and pull out front platform rails to release from latch.
Fold in towards side rails.
3. Lift up inner side rails and fold down to floor.
4. Pull pins at rear rails. Lift up and fold down rear gate to floor.
5. Lift up outer side rails and fold down to floor.