Table 16: Site Preparation Checklist (continued)
DatePerformed ByFor More InformationItem or Task
“Rack Requirements for ACX1000
and ACX1100 Routers” on page 52
“Cabinet Requirements for ACX1000
and ACX1100 Routers” on page 51
Verify that your rack or cabinet meets the
minimum requirements for the installation of
the router.
“Clearance Requirements for Airflow
and Hardware Maintenance on
ACX1000 and ACX1100 Routers” on
page 49
Plan rack or cabinet location, including required
space clearances.
Secure the rack or cabinet to the floor and
building structure.
Cables
Acquire cables and connectors:
•
Determine the number of cables needed
based on your planned configuration.
•
Review the maximum distance allowed for
each cable. Choose the length of cable based
on the distance between the hardware
components being connected.
Plan the cable routing and management.
Related
Documentation
Installing and Connecting an ACX1000 or ACX1100 Router Overview on page 79•
• General Site Guidelines on page 46
General Site Guidelines
Efficient device operation requires proper site planning and maintenance and proper
layout of the equipment, rack or cabinet (if used), and wiring closet.
To plan and create an acceptable operating environment for your device and prevent
environmentally caused equipment failures:
•
Keep the area around the chassis free from dust and conductive material, such as
metal flakes.
•
Follow prescribed airflow guidelines to ensure that the cooling system functions properly
and that exhaust from other equipment does not blow into the intake vents of the
device.