61
Venkon EC 115 V
61
Operation
Operation and Commissioning
Check lter:
-Checktheltertoensurethatitiscleanpriortoinitialstart-up
and replace if dirty.
Water-side check:
- Are all the air passages on the ducts and adapters the correct
size?
- Has an adequate thickness of impermeable insulation been
tted?
-Haveshut-offvalvesbeenttediftheunitistobeoperated
with idle times and the penetration of cold air prevented/
minimised?
IMPORTANT NOTE!
Check the unit for any dirt (packaging waste,
dirt from site etc.) and remove it, if necessary.
Then vent the heat exchanger.