Operation
Operation and Commissioning
7 Operation and Commissioning
Check before initial commissioning whether all necessary
conditions have been met so that the unit can function safely
and properly.
• Structural tests:
-Isthefancoilmechanicallysecureandxedsecurelyinplace?
-Areanycasingssecuredmechanically?
-Areallfancoilcomponentsproperlyinstalled?Operatingthe
unit without a main condensate tray or front panel fan unit is
not permitted and can result in serious personal injury!
• Electrical tests:
-Isallcablinglaidinaccordancewiththeapplicableregulations?
- Are all wires connected in accordance with the wiring
diagrams?
-Istheearthwireconnectedandwiredthroughout?
• Water-side test:
-Istheowandreturnpipeworkproperlyconnected?
-Arethevalvescorrectlytted?(Notethepermittedinstallation
position of the actuators!)
-Areallvalvesandactuatorsworkingcorrectly?
-Aretheshut-offvalveson-siteopen?
• Condensate drain (only with units with a cooling function)
- Is the unit installed with a 1.5% gradient towards the
condensate discharge side.
- Clean the condensate trays before initial commissioning and
remove dirt and site dust.
- Check condensate drain with water
IMPORTANT NOTE!
Refer to the separate instructions for operation
using the Kampmann room controller.
7.1 Pre-Commissioning Checks
Kampmann GmbH can also perform a functional
check (optional). For contact details please refer to
chapter 1.4 „Customer Service“ on page 8.