Grove Published 7-23-2020, Control # 668-02 5-73
GRT9165 OPERATOR MANUAL SET-UP AND INSTALLATION
Connecting Electrical Connection to Main
Boom
Use the following procedure to connect the boom extension
or lattice insert electrical connector to the main boom.
1. Disconnect the boom extension connector from the
stowage bracket (3, Figure 5-60) receptacle.
2. Unwrap excess wire length from the stowage hooks (4)
as necessary.
3. Connect the boom extension or lattice insert electrical
connector (2) to the electrical connector on the main
boom (1).
Disconnecting Electrical Connection from
Main Boom
Use the following procedure to disconnect the boom
extension or lattice insert electrical connector (2,
Figure 5-60) from the electrical connector on the main boom.
Be sure to stow the boom extension or lattice insert electrical
connector on the stowage bracket (3) to prevent water
damage to the connector (2).
1. Disconnect the boom extension or lattice insert electrical
connector (2) from the electrical connector on the main
boom (1).
2. Connect the boom extension connector to the
receptacle on the stowage bracket (3).
3. Wrap excess wire length on the stowage hooks (4).
4. Install protective cap on main boom electrical connector
(1).
Connecting Electrical Connection to Lattice
Insert
Use the following procedure to connect the boom extension
electrical connection to the lattice insert. For more
information about connecting the boom extension to the
lattice insert, see Installing the Boom Extension on the
Lattice Insert, page 5-83.
1. Install the boom extension on the lattice insert. For more
information, see Installing the Boom Extension on the
Lattice Insert, page 5-83.
2. Remove the boom extension connector from the
stowage bracket (3, Figure 5-60) receptacle. Install the
protective cap on the receptacle to prevent water
damage. Unwrap the wire from the hooks (4) as
necessary.
3. Remove protective cap from the lattice insert electrical
socket (5).
4. Connect the boom extension electrical connector (3) to
the electrical socket (5) on the lattice insert. Route the
wire so it does not interfere with crane operation. Store
excess wire on the hooks (4) on the boom extension as
necessary.
Disconnecting Electrical Connection from
Lattice Insert
Use the following procedure to disconnect the boom
extension electrical connection from the lattice insert.
1. Disconnect the boom extension electrical connector (2,
Figure 5-60) from the lattice insert socket (5).
2. Install protective cap on lattice insert socket (5) to
prevent water damage.
3. Remove the protective cap from the stowage bracket (3)
on the boom extension.
4. Connect the boom extension electrical connector (2) to
the stowage bracket (3).
5. Wrap excess wire on the hooks (4) as necessary.
Hydraulic Boom Extension Connections
Use the following procedures to connect and disconnect the
optional hydraulic boom extension to the main boom.
Disconnect and retract the hydraulic lines from the boom
nose whenever the operation of the crane does not require
hydraulic power. This will extend the life of the hose drum,
hoses, and associated hardware. For more information, see
Retracting Hydraulic Hoses for Main Boom Operation, page
5-76.
Checking the Locking Device on the Hose
Drum
The hose drum on the side of the main boom provides the
hydraulic supply to the boom nose hydraulic boom
extension. The hose drum is equipped with a locking device.
The drum must be unlocked before operation.
If the hose drum must be removed, the drum must be locked.
For more information about removing the hose drum, see the
Service Manual.
CAUTION
Equipment Damage Hazard!
Always verify the drum is unlocked before using
extensions or other equipment that require hydraulic
power. Damage to hydraulic hoses or the boom may
occur.