SET-UP AND INSTALLATION MLC650 VPC-MAX™ OPERATOR MANUAL
4-98
Published 04-06-18, Control # 231-14
SHIPPING CRANE COMPONENTS
It is the owner/user’s responsibility to ensure the following:
All trailer loads comply with local, state, and federal
transportation requirements.
All crane components are properly blocked and secured
so they cannot shift or fall off trailers.
To avoid damage to components:
Use synthetic tie-downs to secure components as
shown in Figure 4-81
, View A.
If chain tie-downs are used, install protective covering
(such as sections of rubber tire) between the chain and
the component being secured as shown in Figure 4-81
,
View B.
When securing boom sections, wrap the tie-downs over
the chords — never over the lacings. Keep the tie-downs
as close to the blocking as possible (View A) to prevent
bending the chords.
Item Description
1 Synthetic Tie-Down Wrapped Over Boom Chord
2 Chain Tie-Down Wrapped Over Boom Chord
3 Protective Covering (section of rubber tire)
View A
View B
FIGURE 4-81
Item Description
1 Crawler Blocking (if required per Capacity Chart)
2 Blocking 610 mm (24 in) high
3 Counterweight Link (qty 4)
4 Stop Pin (qty 2)
5 Counterweight Strap (qty 2)
6 Pin with Collar, Retaining Pin, and Cotter Pins (2)
7 Storage Lug (2) (if equipped)
FIGURE 4-82
STORED
WORKING

Table of Contents