MLC650 VPC-MAXâ„¢ OPERATOR MANUAL SET-UP AND INSTALLATION
Detaching the VPC-MAX Beam from the Actuator
See Figure 4-116 for the following procedure.
1. Make sure the pendants (1) are supporting the VPC-
MAX beam (3).
2. Remove the locking pins (4, View A) and disengage both
pin puller keeper plates (5, View B).
3. Store the locking pins (4, View B).
4. Disengage the pin puller pins (6, View B) using the
remote control.
5. Lift the VPC-MAX beam (3, View C) away from the
actuator (7).
6. Prepare the beam for storage or shipping as necessary.
7. Engage the pin puller pins (6, View A) with the remote
control.
8. Remove the locking pins (4, View B) from storage.
9. Engage the pin puller keeper plates (5, View A) and
install the locking pins (4).