User Manual
Page 18
2.3.1 Setting Valve Sequence
The following section provides examples on how to set the valves’ sequence.
Example 1: Cycling Irrigation Program for One Valve
In the following example, Irrigation Program 4 begins running at 8:00 AM. There are two cycles, with one hour in
between each cycle. Irrigation is from one valve. Run Time program 1 and Dosing Program 1 are used.
Example 2: Cycling Irrigation Program for Group of Two Valves
In this example, two valves operate simultaneously (valves operating together is a called a group). All other
specifications are the same as those found in Example 1.
Note: Valves in the same group must have the same run time.
DATE : 19-Apr-07 TIME : 16:12:32
IRRIGATION PROGRAM
Clock Start
Min. Time
2
01:00
Valve #
Run Time #
Dosing Prog
001
1
1
Dose/Water
D