Only qualified personnel are allowed to commission the drive. Read
and follow the safety instructions on the first pages of this manual.
Neglecting the safety instructions can cause injuries or even death.
Ensure that there is no voltage present in the input power terminals
and no voltage can be connected to the drive inadvertently.
This chapter does not include all the tasks to be performed during
commissioning, follow local and national regulations.
In order to carry out a commissioning correctly, we recommend checking the
following steps:
Check the compatibility of the upstream protections (circuit breaker, fuses,
etc...) that could cause an unexpected stop during the soft charge.
Verify that the line voltage is compatible with drive voltage range. If not, the
drive could get damaged.
Connect input, PE and output power wiring, and verify that they are correctly
installed and fastened.