b.
Displays the alignment stake-out data.
Input start chainage, chainage
increment, and the horizontal distance
between side chainage point and central
line. Height distance is required if fill/dig
data is to be staked out.
O/S L: Horizontal distance between the
left chainage point and central line.
O/S R: Horizontal distance between the
right chainage point and central line.
dVD L: Height difference between the left
chainage point and central line
dVD R: Height difference between the
right chainage point and central line.
c.
After the data is input, press [ENT] to
enter into the main screen of displaying
stake-out point and offset. (See the
introduction to Stake-Out Main Menu
behind.)
Here shows the stake-out data of central
line of start chainage.
d.
Steps: Stake out points on the central
line first, and then press [LOFS]( or
[ROFS]) to stake out ( or right)
chainage.
Press [LOFS] (or [ROFS]), the relative
chainage, offset, height difference will be
displayed on the screen.
Chainage and height difference can be
input manually here.
Offset is negative: Offset point is on the
left of central line.
Offset is positive: Offset point is on the
right of central line.
e.
When the chainage and the offset to be
staked out occurs, press [ENT] to enter
to stake-out. Press [ENT] to save the
coordinates of the stake-out point.
Program enters to road stake-out
screen. Not to save, press [SO].