2.4.PRELIMINARY OPERATIONS
Before starting the installation, check what follows:
A)INSTALLATION PLACE SET UP
Check the existing operating lighting.
Check the unit and pit cleaning
Check that the mains electric installation is connected to a suitable earthing
(otherwise stop setting the installation up, until a suitable earthing or grounding is
available).
Check that the unit inlets are perfectly closed.
A storage area next to the unit is to be available, easily accessible to operators and
protected from any adverse weather condition.
Check any cable tray and passing holes suitable for electric cabling, always to be
easily inspected and well-refined.
B)MATERIAL UNLOADING AND WAREHOUSING
Check the Control Panel specifications (Control Panel type, Contactors, Starting,…)
must comply with demanded specifications on the order confirmation.
Check the availability of any suitable material to be used during assembly, referring
to the checklist accompanying the board documents.
Check any unit and material condition when delivery to the site, to check possible
damages which arrived during transportation. Immediately prevent SEA SYSTEMS
Srl in the case of missing units or damages
Store electric and electronic unit in a dry and cold room, in the original packaging.
Should it not be possible, whatever reason, to immediately install the unit,
periodically check stored units to avoid damages depending on a long storage
under unfavourable conditions.
C)SCAFFOLDING
When setting the unit up, use standard scaffolding, exhibiting operating floors at any stop,
at about 0.5 meter lower than the stop.
CAUTION
Scaffolding completely or partially in metal, to be connected to a suitable
grounding, in compliance with safety regulations in force.