Setting functions
8.4 Setpoint calculation
Converter with control units CU250D-2
Operating Instructions, 04/2014, FW V4.7, A5E34261542B AA
135
Table 8- 14 Parameters for setting the scaling
Parameter
Description
p1138
Up ramp scaling
(factory setting: 1)
Signal source for scaling the up ramp.
p1139
Down ramp scaling
(factory setting: 1)
Signal source for scaling the down ramp.
Example
In the following example, the higher-level control sets the ramp-up and ramp-down times of
the inverter via PROFIBUS.
Figure 8-13 Example for changing the ramp-function generator times in operation
Preconditions
You have commissioned the communication between the inverter and the control system.
Free telegram 999 has been set in the inverter and in your higher-level control system.
See also Section: Extend telegrams and change signal interconnection (Page 109).
The controller sends the scaling value to the inverter in PZD 3.
Procedure
To interconnect the scaling of the ramp-up and ramp-down times with PZD receive word 3
from the fieldbus in the inverter, proceed as follows:
1. Set p1138 = 2050[2].
This means that you have interconnected the scaling factor for the ramp-up time with
PZD receive word 3.
2. Set p1139 = 2050[2].
This means that you have interconnected the scaling factor for the ramp-down time with
PZD receive word 3.
The inverter receives the value for scaling the ramp-up and ramp-down times via PZD
receive word 3.