EasyManuals Logo

Siemens SIPROTEC 4 7SD80 User Manual

Siemens SIPROTEC 4 7SD80
416 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #239 background imageLoading...
Page #239 background image
External Initiation Conditions
If the breaker failure protection can be started by external protection devices, the external start conditions
must be checked. Therefore, check first how the parameters of the breaker failure protection are set. See also
Section 2.6.2 Setting Notes, addresses 3901 onwards.
In order for the breaker failure protection to be started, a current must flow at least via the monitored phase
and ground. This may be a secondary injected current.
After every start, the message
50BF Start
(FNo 1461) must appear in the spontaneous or fault annuncia-
tions.
For three-pole starting:
Three-pole starting by trip command of the external protection:
Binary input functions
>50BF Start 3p
and, if necessary,
>50BF release
(in or spontaneous or fault
messages). Trip command (dependent on settings).
Switch off test current.
If start is possible without current flow:
Starting by trip command of the external protection without current flow:
Binary input functions
>50BF STARTw/oI
and, if necessary,
>50BF release
(in or spontaneous or
fault messages). Trip command (dependent on settings).
Busbar Tripping
For testing the distribution of the trip commands in the substation in the case of breaker failures it is impor-
tant to check that the trip commands to the adjacent circuit breakers are correct.
The adjacent circuit breakers are those of all feeders which must be tripped in order to ensure interruption of
the fault current should the local breaker fail. These are therefore the circuit breakers of all feeders which feed
the busbar or busbar section to which the feeder with the fault is connected.
A general detailed test guide cannot be specified because the layout of the adjacent circuit breakers largely
depends on the system topology.
In particular with multiple busbars, the trip distribution logic for the adjacent circuit breakers must be checked.
Here it should be checked for every busbar section that all circuit breakers which are connected to the same
busbar section as the feeder circuit breaker under observation are tripped, and no other breakers.
Auslösung des Gegenendes
Wenn das Auslösekommando des Leistungsschalter-Versagerschutzes auch den Leistungsschalter am Gege-
nende des betrachteten Abzweigs auslösen soll, muss auch der Übertragungskanal für diese Fernauslösung
überprüft werden. Dies geschieht zweckmäßig zusammen mit der Übertragung weiterer Signale gemäß des
Abschnitts “Prüfung der Signalübertragung mit ...” weiter unten.
Termination
All temporary measures taken for testing must be undone, e.g. especially switching states, interrupted trip
commands, changes to setting values or individually switched off protection functions.
Checking the Instrument Transformer Connections of One Line End
If secondary test equipment is connected to the device, it is to be removed or, if applying, test switches should
be in normal operation position.
i
i
NOTE
It must be taken into consideration that tripping can occur even at the opposite end of the protected object
if connections were made wrong.
Before energizing the object to be protected at one end, short-circuit protection must be ensured at least at
the feeding ends. If a separate backup protection (e.g. time overcurrent protection) is available, it has to be
put into operation and switched to alert first.
3.3.8
Mounting and Commissioning
3.3 Commissioning
SIPROTEC 4, 7SD80, Manual 239
E50417-G1100-C474-A2, Edition 02.2018

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIPROTEC 4 7SD80 and is the answer not in the manual?

Siemens SIPROTEC 4 7SD80 Specifications

General IconGeneral
BrandSiemens
ModelSIPROTEC 4 7SD80
CategoryPower distribution unit
LanguageEnglish

Related product manuals