Building Technologies Modular Heating Controller RMH760B CE1P3133en
HVAC Products 3 Commissioning 05.02.2007
Main menu > Commissioning > Wiring test > Heating circuit 1 (or 2 or 3) > Outputs
Operating line Positions
Heating circuit pump Off / On
3.5 Completing commissioning
If the application is valid, the Commissioning menu can be quit as follows:
1.
Press the ESC button. The display shows a menu with the following information:
Caution!
Plant starts
ESC OK
2.
Confirm by pressing the OK knob. Then, the controller starts with the settings
made; the plant is started up, and the Main menu appears on the display.
Main menu:
Commissioning
Heating circuit 1
Heating circuit 2
Heating circuit 2
3.6 Data backup
When commissioning is completed, the entire commissioning data set (configuration
and all settings) can be saved in the controller. If any time later, an unauthorized per-
son readjusts important values, this function can be used to restore the correct con-
trolled state after commissioning.
Main menu > Data backup
Operating line
Adjustable values / display / remarks
Storage date Display of the date on which the commis-
sioning data set was downloaded to the
controller’s memory
Storage year Display of the year in which the commission-
ing date set was downloaded to the control-
ler’s memory
Main menu > Data backup
Operating line
Adjustable values / display / remarks
Restore Caution!
New configuration
Save Caution!
Stored data will be overwritten.
Displays
Setting