7 Commissioning
SMA Solar Technology AG
Operating manualEVC22-3AC-20-BE-en-1058
7 Commissioning
7.1 Procedure for commissioning in combination with
Sunny Home Manager 2.0
This section describes the procedure of commissioning a charging station that is used in systems
with Sunny Home Manager.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure See
1. Commission the charging station. Section7.4, page61
2. Establish a connection to the user interface of the charging
station. There are various connection options to choose
from for this:
• Direct connection via Wi-Fi
• Connection via Wi-Fi in the local network
• Connection via Ethernet in the local network
Section8.1.3, page67
Section8.1.1, page64
3. If required, change the network configuration on the wel-
come page. The automatic network configuration recom-
mended by SMA Solar Technology AG via DHCP server
is activated by default. Only change the network configu-
rations if the default configuration is not suitable for your
network.
Commissioning Assistant
4. Carry out the configuration using the Commissioning Assis-
tant. Select System Manager in the device configuration.
Commissioning Assistant
5. Register the Sunny Home Manager 2.0 and SMA Energy
Meter as SMA Speedwire devices.
Commissioning Assistant
6. Add the charging station as a device to a Sunny Portal
system with Sunny Home Manager 2.0.
SUNNY PORTAL powered
by ennexOS - User Manual
7.2 Procedure for commissioning in stand-alone mode
This section describes the procedure of commissioning a charging station that is used in stand-alone
mode.
Only one device in the system can be used as System Manager at a time (e.g., SMA Data
Manager or a charging station as System Manager). All other devices must be configured as a
subordinate device and recorded in the System Manager.