7 Commissioning
SMA Solar Technology AG
Operating manual EVC22-3AC-20-BE-en-10 63
5. Test the charging station in accordance with
IEC61851 and complete the test report. For an
example of a test report, see the product page at
www.SMA-Solar.com.
6. If the green and red LEDs flash simultaneously during commissioning, operation is stopped
because the commissioning procedure has not been (fully) carried out. For the charging station
to begin operation, the configuration must be completed.
7. If the green LED is still flashing, the conditions for activating charging operation are not yet
met. As soon as the conditions for charging mode are met, the charging station starts charging
and the green LED lights up continuously, depending on the available power level.
8. If the red LED lights up, an event has occurred. Find out which event has occurred and, if
necessary, initiate countermeasures.
9. Ensure that the charging station is charging properly.
Transfer to the operator
When installation and commissioning are complete, give all documentation to the operator.
The operator must be instructed on the following points:
Safety when using the charging station
Appropriate procedures for inspecting and maintaining the charging station
Meaning of the LED indicators
Position and function of the AC miniature circuit breaker to switch off or restart the
charging station
Contact partner in case of problems
Access to the Sunny Portal (powered by ennexOS)
SMA Energy App