Operating Instructions 6-26
Post Load Procedure
1. Make sure all the doors are closed and locked.
2. Make sure the setpoint is at the desired setting.
3. Start the unit.
4. A half hour after loading, defrost the unit by manually initiating a defrost cycle. If the evaporator coil temperature is below
7 C (6 C on units with a TG-V controller; 3 C on units with a TG-IV controller), the unit will defrost. The defrost cycle should
terminate automatically.
TG-VI, MT µP-V AND µP-VI NOTE: A manual defrost function is built into the controller. Press SELECT key (MODE key
on µP-VI) (MANUAL DEFROST key on SR-2/SR-3) to scroll to the dEF screen in the menu display. Then press the ENTER
key to initiate Defrost. The display will briefly show Lod (load) and enter Defrost.
Post Trip Inspection
1. Wash the unit.
2. Check for fluid leaks.
3. Check for loose or missing hardware.
4. Check for physical damage to the unit.