86
15. DISTANCE MEASUREMENT
An REM measurement is a function used to measure the height to a point where a target cannot be
directly installed such as power lines, overhead cables and bridges, etc.
The height of the target is calculated using the following formula.
Ht = h
1
+ h
2
h2 = S sin
z1
x cot
z2
- S cos
z1
It is possible to allocate softkeys in measurement menus to suit various applications and the ways
that different operators handle the instrument.
"22.6 Allocating Key Functions"
PROCEDURE
1. Set the target directly under or directly over the
object and measure the target height with a tape
measure etc.
Press [HT] and enter the target height.
2. Select "REM" in <Menu>.
15.4 REM Measurement
Zenith
Zenith

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Topcon DS Series and is the answer not in the manual?

Topcon DS Series Specifications

General IconGeneral
BrandTopcon
ModelDS Series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals