SmartCabinet2-E Series Computer Room Solution Product User Manual
22 Chapter 2 Product Installation And Commissioning
Table 2-6 Installation Inspection
The cabinet feet support the ground and the cabinet is leveled
The drain hose is tightly fastened, and the other end of the drain pipe is placed in the floor drain
The cabinet is neat and tidy without spray defects
The door can be opened and closed flexibly, and the door lock can be normally used.
The labels and logos are complete and clear
The ECO fan module is installed firmly and reliably, and when manually shaking the module,
there is no abnormal sound.
The battery and uninterruptible power supply are installed firmly and reliably, and there is no
abnormal noise when manually shaking the cabinets.
The top guard ring is correctly installed
The user's power cord and communication cable are reliably connected, and the binding is firm
and tidy.
The ECO fan module cable is reliably connected, and the binding is firm and tidy.
The battery power cable and communication cable are connected reliably.
2.3 Software and Hardware Commissioning
2.3.1 Commissioning process
The SmartCabinet2-E commissioning process is shown in the Figure 2-30.
Figure 2-29 Commissioning Flowchart
2.3.2 Preparation
The product commissioning is used to support the commissioning scenario in product deployment. Prior to starting
the commissioning, the equipment status must meet the following conditions:
The hardware installation and inspection work has been completed, the installation wiring is in place correctly.
2.3.3 Inspection
Prior to powering on the SmartCabinet2-E product, check the following list:
Table 2-7 Pre-commissioning checklist