4.1 Packaging Material
All material used to package this unit is recyclable. Please save for future use or dispose of the
material appropriately.
4.2 Handling the Unit while Packaged
Transport the unit with a forklift or pallet jack. See Moving 600-mm (24-in.) Models Using Rigging below
for additional handling option for the 600-mm (24-in) unit.
When using a forklift or pallet jack:
• Make sure that the forks (if adjustable) are spread to the widest allowable distance that will fit
under the skid.
• Make sure the fork length is suitable for the skid length. Skid length for 600-mm (24-in.) model
is 60in (1524mm). Skid length for 300-mm (12-in.) model is 54in. (1372mm)
• Do not lift the packaged unit any higher than 4in. (102 mm). All personnel except those
moving the unit must be kept 12ft (3.7m) or more from the unit while it is being moved.
• If the unit must be lifted higher than 4in. (102 mm), all personnel not directly involved in
moving the unit must be 20ft (5m) or more from the unit.
• Always refer to the location of the center-of-gravity indicators when lifting the unit, see Figure
4.1 below.
Figure 4.1 Center-of-gravity indicator
4.2.1 Moving 600-mm (24-in.) Models Using Rigging
1. Use a pallet jack or forklift to raise the packaged unit.
2. Place slings under the skid runners, equally spacing the slings to make sure the unit is
balanced, see Figure 4.2 on the facing page.
3. Lower the unit and remove the pallet jack or forklift.
4. Connect the slings to the lifting device, using spreader bars or similar equipment to protect the
unit, see Figure 4.2 on the facing page.
NOTE: Wrapping one or two more straps around the middle of the unit will improve stability when it is
lifted.
5. Move the unit to its installation location. Two or more properly trained and qualified personnel
are required to move the unit to its installation location.
6. Lower the unit and remove the slings.
Vertiv | Liebert CRV Installer/User Guide | 20