NoteAction
ELECTROSTATIC DISCHARGE (ESD)
The unit is sensitive to ESD. Before handling the
unit please read the safety information in the sec-
tion The unit is sensitive to ESD on page 31
2
Art. no. is specified in Required
equipment on page 136.
Reconnect the battery cable and install the battery
pack into the SMB/battery recess.
Note
RMU batteries are installed together with a battery
holder to be properly secured inside the recess.
See figure.
3
Shown in figure Location of SMB
battery on page 135.
xx1300000307
A Battery pack RMU
B Battery holder
C Battery cable
D Strap
Strap the battery cable to the holder.
Shown in figure Location of SMB
battery on page 135.
Secure the SMB battery cover with its attachment
screws.
4
Detailed in chapter Calibration -
section Updating revolution coun-
ters on page 356.
Update the revolution counters.5
DANGER
Make sure all safety requirements are met when
performing the first test run. These are further
detailed in the section First test run may cause
injury or damage on page 26.
6
138 Product manual - IRB 760
3HAC039838-001 Revision: M
© Copyright 2011-2018 ABB. All rights reserved.
3 Maintenance
3.4.5 Replacing the SMB battery
Continued