NoteAction
Use a cutting torch with a long shaft.Cut the coils of the springs inside the
housing as specified below:
• Outer spring: cut at least five coils!
• Outer spring: cut at least eight coils!
• Middle spring: cut at least four coils!
• Inner spring: cut at least four coils!
• Inner spring: cut at least eight coils!
6
Double-check the number of coils cut and
make sure all the tension in the springs is
removed.
7
Double-check the number of coils cut and
make sure all the tension in the springs is
removed.
Cut more coils if there is still tension in the
springs.
380 Product manual - IRB 760
3HAC039838-001 Revision: M
© Copyright 2011-2018 ABB. All rights reserved.
6 Decommissioning
6.3 Decommissioning of balancing device
Continued