5.0 Introduction
Within this section we have set out the necessary information to ensure
the safe and correct method of installi ng the machine. Set out below is the
instructions and guide lines to de scribe how the operation should be un-
dertaken.
5.1 Lifting points
The machine shall be lifted/transported by means of a crane. On the main
machine there are mounted lifting hoo ks for this purpose. Lifting
hooks/places are shown on the following drawing, Figure 3 - Pos. 1.
Figure 3
Other machine parts are lifted by forkli ft/strap. The strap is placed suitable
regarding the centre of gravity.
If you are in any doubt regarding safe li fting, seek advice from a specialist
lifting company.