5.4 Dimensions of clearance needed for service and maintenance
To be able to carry out service and ma intenance work on the machine in a
safe and efficient way it will be necessary with a clearance of minimum 1-
meter around the machine.
5.5 Power and service details and requirements
For electrical tools and lightening dur ing mounting and maintenance of the
machine it is necessary to have a s eparate power supply, as the machine
must be disconnected and locked during this kind of work on the machine.
5.6 Test before starting
Rotating direction of the motor:
Before the machine starts operating, it is necessary to inspect the motor to
ensure it is rotating in the right direct ion. A painted arrow on the fan cover
indicates this. If the motor rotates in the wrong direct ion, an authorised
electrician should alter the direction of rotation.
Rotating direction of the rotor:
To check the setting of this machine, it is necessary to rotate the rotor, to
see if the setting is correct. This can be done manually by turning the
clutch between the motor and the reduction gear
Remember the machine should be turned off and all main switches
should be locked before working on the machine.
5.7 Foundations
Under the machine a certain depth of re inforced concrete is necessary to
avoid vibration damages etc.
Under this machine it is necessary to cast a foundation of reinforced con-
crete in depth of 400 mm. The foundat ion needs a supporting surface of
compacted sand basis.