2. Commissioning
2-3
Festo Festo P .BE CP FB13-E-EN en 9910c
2.1 Preparing the CP system for operation on the PROFIBUS-DP
2.1.1 Operating voltage
Please note
Use a suitable power unit to supply the CP field bus node
with operating voltage (see theCP system)manual.
2.1.2 Saving the string assignment
Please note
Before commissioning the CP system:
Prepare the CP system for commissioning (see CP sys-
tem manual).
Before commissioning the CP system on the PROFIBUS-DP,
proceed as follows:
1. Connecting the operating voltage for the node (see
CP system manual).
2. Connecting the CP modules
3. Switching on the operating voltage
4. Saving the string assignment by pressing the SAVE button