14 Chapter 2 Installation and Cabling
Ehave Series Full Digital IGBT CO
2
/MAG/MMA Multifunctional Inverter Welder User Manual
Safety Warning
When the operating site is wet and the welder is used on an iron plate or frame, install a ground fault
circuit interrupter (GFCI).
2.4 Open-Package Inspection
When opening the package, perform the following inspection carefully:
1. Check whether the product is broken or damaged.
2. Check whether the rated values on the label are consistent with your order.
The product and its package have been carefully checked before delivery. If you identify a
problem, contact us or your supplier as soon as possible.
You can open the package and perform inspection only after the product arrives at the
installation site. Product inspection must be performed jointly by the user's representatives and
Megmeet's representatives.
The inspection procedure is as follows:
1. Open the package to which the packing list is attached.
2. Take out the packing list.
3. Check the parts against the packing list.
4. Check the quantities and SNs specified on the package.
5. Check whether all the expected parts are delivered.
6. Check the quantities and types of accessories.
7. Check whether the product is intact.
2.5 Preparing the Cable Bundle
Note
1. Connect this welder only to the matching or specified wire feeders, welding torches, and gas
regulators. Otherwise, the welding performance and quality will be affected.
2. If you need to extend a power cable, use the power cables and gas tubes specified in this user
manual.
3. If the cable bundle will be dragged with force, the force must be imposed on both ends of the short
power cables, so as to protect the 7-core control cable.
2.5.1 Packing List for the Cable Bundle Component Box
Table 2-3 and Table 2-4 provide packing lists of cable bundle component boxes.