Operation Manual ServoOne Supply Unit
59
ID no.: 1101.21B.6-00 Date:04/2020
5 Commissioning
5.1 Notes for operation
CAUTION! Damage to the device due to incorrect installation conditions!
The device may be irreparably damaged due to detrimental ambient
conditions during operation.
Forthisreason
• Moisturemustnotbeallowedtoenterthedevice
• Theremustnotbeanyaggressiveorconductivesubstancesintheambientair
• Foreignbodiessuchasdrillingchips,screws,washersetc.mustnotbeallowedtofallinto
thedevice
• Coolingopeningsmustnotbecovered,i.e.coolingairmustbeabletoowunhindered
throughthedeviceandthemainsconnectioncomponents.
Further information on ambient conditions can be found in the appendix.
5.2 Initial commissioning
(operation via terminals)
The commissioning of the supply unit is described in the following. During this process
the device is controlled via the control terminal X4. The setpoint for the DC link voltage is
specied internally as a xed value. Commissioning is divided into the following steps:
DANGER! Risk of injury due to electrical power!
• Carelessness will result in serious injuries or death.
Nevermakeordisconnectelectricalconnectionswhiletheyareelectricallylive!Beforemaking
anychange
thedeviceistobedisconnectedfromthemains.Dangerouslyhighvoltages≥50Vcanbe
presentontheDClinkconnectionsandothercomponentsinthemainsinputareaafterpower
off.Socheckthatelectricalpowerisnotpresent!Seechap.4.1.
1.
Wiring the components
See chap.4.3, p.33 and subsequent information.
2.
Switch on control voltage
External 24-V supply voltage
See chap.4.7.1, p.44 BG5 and BG6a. See chap.4.7.2, p.45 BG7.
3.
Establish communication with DriveManager 5
You will nd information on installation in the Installation Manual DriveManager
5 as well as in the online help.
4.
Adapt to the parameters for the supply system
5.
Automatic identication of the DC link capacitance and the equivalent time
constant for the current regulation
6.
Congure the controller parameters for the DC link capacitance
See chap.5.2.7, p.63.
7.
Congure the controller parameters for the DC link voltage
See chap.5.2.8, p.64.
8.
Set monitoring of the braking resistor
See chap.5.2.9, p.64.
9.
Switch on the mains supply voltage via main switch
10.
Switch on the regulation
Start with ENPO set to HIGH.