5-82 Published 7-23-2020, Control # 668-02
SET-UP AND INSTALLATION GRT9165 OPERATOR MANUAL
a. Hold the handle (1, Figure 5-68) and remove
retaining clips (2) and pins (3).
b. Swing the mast sheave assembly (4) to the raised
position. Align the holes.
c. Install pins (3). Secure with retaining clips (2).
5. Tie a tag line (1, Figure 5-69) to the end of the lattice
insert section (2).
6. Lift the lattice insert in front of the nose of the main boom
(3) so the four pin holes align on both sides.
7. Install pins (4) and retaining clips (5).
8. Remove pins (4) from the holders.
9. Insert pins (4) into the connecting points. Secure the
pins with retaining clips (5).
10. Connect lattice insert section electrical connector to the
main boom electrical connector.
11. If installing a hydraulic boom extension to the lattice
insert section, connect the hydraulic connectors and if
needed, route the hoses the length of the lattice insert.
12. Install the boom extension. For more information, see
Installing the Boom Extension on the Lattice Insert, page
5-83.
1
1
2
3
4
4
2
3
Lowered
Raised
FIGURE 5-68
10016
10017
10018
1
4
5
2
FIGURE 5-69
3
3
Both Sides
9915
10014

Table of Contents

Other manuals for Manitowoc Grove GRT9165

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GRT9165 and is the answer not in the manual?

Manitowoc Grove GRT9165 Specifications

General IconGeneral
BrandManitowoc
ModelGrove GRT9165
CategoryConstruction Equipment
LanguageEnglish

Related product manuals