Manitowoc Published 04-06-18, Control # 231-14 4-27
MLC650 VPC-MAXâ„¢ OPERATOR MANUAL SET-UP AND INSTALLATION
See Figure 4-26 for the following procedure.
6. Attach the pendants (1, View E) from the assist crane to
the lifting lugs (2) on the VPC-MAX beam (3).
7. Remove the locking pins (4, View A) and disengage both
pin puller keeper plates (5, View B).
8. Store the locking pins (4, View B).
9. Disengage the pin puller pins (6, View B) using the
remote control.
10. Lift the VPC-MAX beam (3, View C) into position at the
actuator (7).
11. Using the alignment pins (8, View C), align the pin
holes (9) in the VPC-MAX beam (3) with the pin holes in
the actuator.
12. Engage the pin puller pins (6, View A) with the remote
control.
13. Remove the locking pins (4, View B) from storage.
14. Engage the pin puller keeper plates (5, View A) and
install the locking pins (4).
15. Turn off the cab power and the remote control key.
CAUTION
Equipment Damage!
The actuator can damage components if it moves
unexpectedly.
Make sure to lock out the VPC-MAX actuator.