Service Manual 0070-10-0556-02 5 - 1
5.0
Preventative Maintenance
5.1 Preventative Maintenance Schedule
The following is a list of activities required for periodic maintenance of the Spectrum
®
/
Spectrum OR
™
monitor. The physical inspection, replacement of consumable items and
performance checks should be performed at the recommended intervals stated below.
Manufacturer is not responsible for component failure or loss resulting from the use of stated
consumable items beyond their recommended replacement interval.
5.1.1 Mechanical / Physical / Visual Inspection - Perform At Twelve
Month Intervals
Suggested Inspections for Wear and Abuse:
1. Outercase, Line Cords, Rolling Stands, Wall Mounts, Modular Accessories and
Interconnecting Cables.
2. Patient Interface Connections (ECG, IBP, SpO
2
, Temp, CO
2
and NIBP)
5.1.2 Perform Verification and NIBP Calibration – Annually
1. See NIBP Verification in Section 4.6.6 for test outline.
2. See Microstream
®
CO
2
Calibration in Section 4.5 for calibration outline.
5.1.3 Perform Verification and CO
2
Calibration
1. See CO
2
Operation Verification in Section 4.6.8 test outline.
2. Replace the CO
2
assembly after 20,000 operating hours or as required by the service
code.