NIBE FIGHTER 1250
B
General description Notes Signature Date
Brine
System fl ushed
System vented
Antifreeze
Level vessel
Particle fi lter
Safety valve
Shut-off taps
Heating medium
System fl ushed
System vented
Expansion vessel
Particle fi lter
Safety valve
Shut-off taps
Electricity
Fuses heat pump
Fuses property
Outside sensor
Current transformers
Isolator switch
Earth circuit-breaker
Checklist: Installation inspection of FIGHTER1250
Present regulations require the heating installation to be
inspected before it is commissioned. The inspection must
be carried out by a suitably qualifi ed person and should be
documented. The above applies to closed heating systems.
If the heat pump is replaced, the installation must be in-
spected again.
Inspection of the installation
Inspection of the installation

Table of Contents