10
Introduction
CB 240 Climbing Formwork
Instructions for Assembly and Use – Standard Configuration
Preparation
1. Assemble wall formwork.
2. Assemble platforms.
3. Assemble finishing platform.
Standard Work Flow
10. Place formwork on platform unit and
secure.
11. Clean formwork and adjust if
necessary.
12. Reinforce second wall section.
13. Mount leading anchor and close
formwork.
14. Place formwork anchor.
15. Pour second wall section.
16. Remove advancing bolts and retract
formwork.
17. Mount scaffold mounting rings.
Initial use
1. Position wall formwork for first wall
section.
2. Add reinforcement to first wall
section.
3. Mount leading anchor and close
formwork.
4. Place formwork anchor.
5. Pour first wall section.
6. Remove advancing bolts and strike.
7. Mount scaffold mounting rings.
8. Attach platform unit.
9. Mount wind bracing if required.