© İnnosis Makine 38
Fig.19 Pile Extracon
IMPORTANT: For extracng the operator has to use the approved the pile extractor and must
maintain regular inspecons for wear and tear. If wear exists please replace.
3-5 End of Day Operaons
At the end of a working day, the operator must close all the hydraulic rams, and lock up all
lockable components.
4- COMPONENTS SUBSTITUTION AND VARIOUS REGULATIONS
4-1 Changing of the pile hammer temple and the pile hammer
Depending on their use, piles may have dierent secons and therefore the pile hammer
template and the pile hammer have to be adapted to each pile secon. If it is necessary to drive
piles with a dierent secon from the standard ones, it would be necessary to change both pile
hammer and pile hammer template on the hammer group. Both accessories are produced by
the company Quantum and are delivered to the Customer only on request. The instrucons for
the substuon of the pile hammer template and the pile hammer are described as follows: