95
Dig/fill is decided via the estimated height of hinge point. If the height is above the hinge point, the dig slope
is used; otherwise the fill slope is used.
STEP
OPERATION
DISPLAY
a.
In the Stake-out main menu, input (or
select) the side chainage to be slope
staked out. Press [MENU] to start.
[MENU]
CH:
1.000
O/S:
0.000m
dVD:
0.000m
* Press [MENU] Slope SO
LOFS
ROFS
+CHG
-CHG
b.
Input the ratio of left and right slopes to be
filled (or digged). After finishing inputting
one item, press [ENT].
Input slope
+
[ENT]
Slope
SO
(1:N)
Cut L:
0.000
Fill L:
0.000
Cut R:
0.000
Fill R:
0.000
c.
When all data are input, select the left (or
right) slope to be staked out.
Select (Left) or (Right)
Cut L:
1.000m
Fill L:
2.000m
Cut R:
2.000m
Fill R:
3.000m
Left
Right