Commissioning
5.4 Basic commissioning with IOP
Converter with control units CU250D-2
Operating Instructions, 04/2014, FW V4.7, A5E34261542B AA
67
Set the Ramp Up time in seconds.
This is the time the Inverter/motor system will take from
being g
iven the run command, to reaching the selected
Set the Ramp Down time in seconds.
This is the time the Inverter/motor system will take from
bein
g given the OFF1 command, for the motor to reach
A summary of all the settings is display.
If the settings are correct, select Continue.
The final screen gives two options:
Save settings
Cancel Wizard
If save is selected, a factory reset will be performed then
the settings are saved to the Inverter
memory. The
location of safe data is assigned using the "Parameter
saving mode" function in "Parameter settings" in
"Menu".
The basic commissioning of your converter is finished.