Commissioning
8.5 Commissioning TM54F by means of STARTER/SCOUT
Safety Integrated
Function Manual, 05/2010, A5E03264275A
199
8.5 Commissioning TM54F by means of STARTER/SCOUT
8.5.1 Basic sequence of commissioning
The following conditions must be met before you can configure the TM54F:
● Concluded initial commissioning of all drives
Table 8- 2 Configuration sequence
Step Execution
1 Insert the TM54F
2 Configure the TM54F and generate the drive groups
3 Configure the drive groups
4 Configure the inputs
5 Configure the outputs
6 Copy the parameters to the second drive object (TM54F_SL)
7 Change the safety password
8 Activate the configuration by selecting "Activate settings"
9 Save the project in STARTER
10 Save the project in the drive by selecting "Copy RAM to ROM"
11 Execute POWER ON
12 Acceptance test