Commissioning   
8.11 Information pertaining to component replacements 
  Safety Integrated 
238  Function Manual, 05/2010, A5E03264275A 
5.  Carry out a POWER ON (power off/on) for all components. 
 
 
 
Note 
In this case, the system will not notify you with a flashing LED that a POWER ON is 
required. 
 
6.  Carry out an acceptance text and acceptance report according to Chapter "Acceptance 
test and acceptance report" and table "Effect of the acceptance test for certain 
measures". 
 
WARNING 
 
Before re-entering the danger area and before resuming operation, a (partial) acceptance 
test must be carried out for all the drives affected by the component exchange (see the 