7. First start-up
- 86 -
951-180-083-EN
Version 01
Checklist for first start-up
7.3 Inspections before rst start-up
YES NO
Electrical connection (inductive NAMUR sensor) established correctly
Mechanical connection established correctly
The performance characteristics for the aforementioned connections match the
specifications in “Technical data.”
All components such as lubrication lines and metering device are correctly mounted.
Product is protected by a suitable pressure relief valve.
No apparent damage, contamination, or corrosion
Any dismantled protective and monitoring equipment is fully reinstalled and functional
Equipotential bonding fully present, properly connected, and electrically continuous
No accumulated dust present
7.4 Inspections during initial commissioning
No unusual noises, vibrations, moisture accumulation, odors present
No undesired discharge of lubricant at connections (leakage)
Lubricant is fed without bubbles
The bearings and friction points requiring lubrication receive the planned lubricant
volume
To ensure safety and functionality, the per-
son specified by the operator is required
to perform the following inspections. Any
detected deficiencies must be resolved im-
mediately. The correction of deficiencies
must be done exclusively by a specialist
competent and authorized to do so.
VP VPK
Plug screw, left
and right metering
device side
VPB
Fig. 39 Position of plug screws

Table of Contents

Other manuals for SKF VP Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SKF VP Series and is the answer not in the manual?

SKF VP Series Specifications

General IconGeneral
BrandSKF
ModelVP Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals