AT LEAST THE FOLLOWING STEPS OF THE START-UP QUICK GUIDE MUST BE PERFORMED
DURING THE INSTALLATION AND COMMISSIONING.
IF ANY PROBLEMS OCCUR, CONTACT YOUR LOCAL DISTRIBUTOR.
Start-up Quick Guide
1. Check that the delivery corresponds to your order, see Chapter 3.
2. Before taking any commissioning actions read carefully the safety instructions in
Chapter 1.
3. Check the size of the motor cable, mains cable, mains fuses and check the cable
connections, read Chapter 6.1.1.1 – Chapter 6.1.2.
4. Follow the installation instructions.
5. Control connections are explained in Chapter 6.2.2.
6. Ensure the adequate pressure and flow of the cooling agent you are using. See
Chapter 5.2.
7. If the Start-Up wizard is active, select the language of the keypad and the application you
want to use and confirm by pressing the Enter button. If the Start-Up wizard is not
active, follow the instructions 7a and 7b.
7a. Select the language of the keypad from the Menu M6, S6.1. Instructions on using the
keypad are given in Chapter 7.
7b. Select the application you want to use from the Menu M6, S6.2. Instructions on using
the keypad are given in Chapter 7.
8. All parameters have factory default values. In order to ensure proper operation, check
the rating plate data for the values below and the corresponding parameters of
parameter group G2.1.
• nominal voltage of the motor
• nominal frequency of the motor
• nominal speed of the motor
• nominal current of the motor
• motor cos
ϕ
All parameters are explained in VACON
®
NX All in One Application Manual.
9. Follow the commissioning instructions, see Chapter 8.
10. The VACON
®
NX Liquid-Cooled AC drive is now ready for use.