04-800 Duplex Fan 1 Locked RAP
04-800 The machine has detected a fault with duplex fan 1.
Procedure
WARNING
Switch off the electricity to the machine. Disconnect the power cord from the customer
supply while performing tasks that do not need electricity. Electricity can cause death or
injury. Moving parts can cause injury.
Go to the relevant procedure:
• 4150 Checkout
• 4250/4260 Checkout
• 4265 Checkout
4150 Checkout
NOTE: The main PWB has test points. The location of the test points is shown on the Main
PWB PJ location illustration.
Refer to Wiring Diagram 7. Perform the following:
1. Switch off the machine, then switch on the machine.
2. Enter dC330 code 04-400 and 04-410. Check that the duplex fan 1, PL 7.35 Item 16 runs
at normal speed.
3. Check the wiring between the duplex fan 1 and CN25 on the Main PWB.
4. Install new components as necessary:
• Duplex fan 1, PL 7.35 Item 16.
• Side cover assembly, PL 7.30 Item 1.
5. Perform the OF5 Main PWB Check RAP.
4250/4260 Checkout
NOTE: The main PWB has test points. The location of the test points is shown on the Main
PWB PJ location illustration.
Refer to Wiring Diagram 25. Perform the following:
1. Switch off the machine, then switch on the machine.
2. Enter dC330 code 04-400 and 04-410. Check that the duplex fan 1, PL 7.35 Item 16 runs
at normal speed.
3. Check the wiring between the duplex fan 1 and CN17 on the Main PWB.
4. Install new components as necessary:
• Duplex fan 1, PL 7.35 Item 16.
• Side cover assembly, PL 7.30 Item 1.
5. Perform the OF5 Main PWB Check RAP.
4265 Checkout
NOTE: The main PWB has test points. The location of the test points is shown on the Main
PWB PJ location illustration.
Refer to Wiring Diagram 41. Perform the following:
1. Switch off the machine, then switch on the machine.
2. Enter dC330 code 04-400 and 04-410. Check that the duplex fan 1, PL 7.35 Item 16 runs
at normal speed.
3. Check the wiring between the duplex fan 1 and CN31 on the Main PWB.
4. Install new components as necessary:
• Duplex fan 1, PL 7.35 Item 16.
• Side cover assembly, PL 7.30 Item 1.