HVC 450 kW E-Bus Charger Installation Guide
Revision: 1.2 COMPANY CONFIDENTIAL
Date released: 16-08-2018 Page 109 of 128
6. Commissioning
6.1. Commissioning preparation
Commissioning is the last phase necessary to get the HVC 450 kW E-Bus Charger into
operation.
The planning steps for the commissioning phase are shown in the figure below.
D Commissioning
The commissioning of the HVC 450 kW E-Bus Charger need to be performed by a service
engineer from the ABB Delivery department and/or a certified local ABB service engineer.
Both will need the support from the local contractor.
Before the service engineer can start, the following conditions must be met:
All installation work is done.
Grid power is available.
A local technician is present for assistance and to switch the power on.
Boom lift available to check all the connections on the pantograph.
An electric or hybrid bus available to perform the functional tests.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB HVC and is the answer not in the manual?

ABB HVC Specifications

General IconGeneral
BrandABB
ModelHVC
CategoryBattery Charger
LanguageEnglish

Related product manuals