Installation
2-2 TM-F1OP-C1XN-01
Introduction
This section provides recommendations and procedures for inspecting,
installing, and testing the power supply.
Basic Setup Procedure
See Table 2-1 for a summary of the basic setup procedure and an overall
view of the subsections in this section. Use the procedure as a quick
reference if you are familiar with the installation requirements for the
power supply. If you want more information, each step in the procedure
refers to subsequent sections which contain more details. Execute each
step in the sequence given.
See “Local Operation” for instructions for front panel operation, OVP and
OTP, shutdown, and using multiple supplies. You will find remote
programming and monitoring described in “Remote Operation”.
Table 2-1
Basic Setup Procedure
Step # Description Action Reference
1 Inspection Perform an initial physical inspection
of the supply.
“Inspection, Cleaning, and
Packaging” on page 2–3
2 Installation Install the supply (bench or rack
mount), ensuring adequate ventilation.
“Location, Mounting, and
Ventilation” on page 2–5
3 Input Power Connect AC input power. “AC Input Power Connection” on
page 2–6
4 Test Perform functional tests for voltage
mode operation, current mode
operation, and front panel controls.
“Functional Tests” on page 2–10
5 Load Connect the load. “Load Connection” on page 2–13
6 Sensing Connect sense lines. “Local and Remote Sensing” on
page 2–23
TM-F1OP-C1XN-01.book Page 2 Thursday, October 25, 2007 9:04 PM