Commissioning
34
isoxx1685Dx-x25_D00272_07_M_XXEN/09.2022
6.3.8 TEST
Start the device test.
During the test, all relays switch and the ALARM 1 and ALARM 2 LEDs light up briefly.
6.4 Recommissioning
If the device has already been put into operation before, the self test will be started shortly af-
ter the supply voltage has been connected. Restart the commissioning wizard using the fol-
lowing menu path:
Menu/Device settings/Commissioning
This menu can be used to modify previously made settings.
If the device has been commissioned before, the self test is not performed again. It can be
called up via the "Control" menu (refer to page 62).
Observe device status!
Once initial commissioning has been completed and the initial measurement
taken, the device changes from the alarm state to normal state by adhering
to the set response values.
TEST
x.x.x
Start test?
Relays can switch.
Cancel TEST