Installation
17–6
1070 072 145-102 (01.07) GB
17.2.6 Capacitive Load in Power Supply Network
All CL200 modules contain capacitive interference suppression measures
installed between the power supply lines and protective earth. This fact must
be taken into account when employing an earth-leakage monitoring device.
Module 24 V ³ PE 0 V ³ PE
NT200 5 nF 100 nF
ZE200 – 10 nF
ZE200A – 10 nF
ZE200M – 25 nF
ZE200AM – 25 nF
ZE201 – 10 nF
ZE200-DP /
ZE200A–DP
– 20 nF
E24V– (16-way) 5 nF 10 nF
E24V– (32-way) 5 nF 10 nF
E16/A8 5 nF 15 nF
E16/A16 5 nF 15 nF
A24V–/0.5A (16-way) 15 nF 15 nF
A24V–/0.5A (32-way) 30 nF 30 nF
A24V–/2A 10 nF 15 nF
AR/2A 15 nF 5 nF
E ana 25 nF 25 nF
E20 ana 25 nF 25 nF
A ana 5 nF 5 nF
A20 ana 25 nF 25 nF
A10 ana (4) 25 nF 25 nF
A10 ana (8) 25 nF 25 nF
R200 – –
R200P – –
COM2–E – –
POS–SA1 15 nF 15 nF
POS–SA2 25 nF 25 nF
POS–LR1 15 nF 15 nF
POS–LR2 25 nF 25 nF
BM–ASI – –
DP–EA4 – –
AG/S – –
RM2–DP12 4.7 nF 4.7 nF