Module Racks
3–3
1070 072 145-102 (01.07) GB
Clear space
Clear space
45 + cable
channel
45 + cable
channel
Clear space
100 + cable
channel
100 + cable-
channel
100 + cable
channel
[Dimensions in mm]
Installation
The GG3 / GG3-K module rack can be secured in one of the following ways:
D Screw mounted surface installation
D Installation via locking foot, and insertion in 35 x 7.5 mm support rail, as
per EN 50022.
. The locking foot is not supplied as standard equipment with the mo-
dule racks, and must be ordered separately (refer to page 3–1).
Screw mounted surface installation, drilling template
GG3K : 58.6
GG3 : 150
36.75
( 183.8 )
( 10.7 )
( 162.4 )
96.5
( 10.7 )