T-code Valid from serial number
403-414, 669-671, 716-718 713962-
Date Order number
2005-09-09 218920-040
5- 4 Service Manual REFLEX RR B,E RR B,E CC © BT Europe AB
Preventive maintenance – P2
Maintenance Schedule
6000 Hydraulic system
6110.1 Check the tank, mounting and leakage X
6110.2 Check oil levels X
6110.3 Clean or replace the oil B
6120.1 Check the hoses, pipes and couplings U X
6120.2 Check for wear to hoses on the mast and
reach carriage
X
6130.1 Change air and oil filters X
6170.1 Check overflow pressure X
6600 Cylinders
6600.1 Check for leakage U X
6600.2 Check the mountings X
7100 Mast and reach carriage
7100.1 Check the lowering speed X
7100.2 Check for cracks or damage X
7110.1 Lubricate mast beams by the runners F
7120.1 Check for wear on lifting chains and
sprockets
X
7120.2 Check adjustment of lifting chains Check
chain bolts and chain mountings. Check
and tighten the lock nuts and inspect the
safety pins on all chains
X
7120.3 Lubricate lifting chains D
7150.1 Check for play on rollers X
7190.1 Check and tighten mast mounting X
7200.1 Check the function of accessories U X
7400.1 Check for wear to the forks and other lift-
ing devices
U X
7400.2 Check for damage and deflection on the
forks and other lifting devices
U X
Table 4: Maintenance schedule RR B/E 1-8
Pos.
no.
Work to carry out
Interval in hours 5 20 250 500 1000 3000
Interval in days/weeks/months 1 d 1
wk
3 m 6 m 12 m 36 m