4 COMMISSIONING
4.1 PRE-COMMISSIONING TASKS
The equipment is easily commissioned, once the front cover is removed, programming of the equipment
can be done either by press the one click smart setup button or software commissioning via Micro-USB
interface.
4.2 LED INDICATORS
Three diagnostic LEDs are located on mPICO panel; each indicates the status of a particular function:
Table 6: mPICO LED
Identifier
Colour
Indication
RUN
Green
Operation indicator, flashes every second to indicate normal operation.
PWR
Red
Power indicator. ON = power on; OFF = power off
ALM
Red
Alarm indicator. ON = alarm; OFF = no alarm
4.3 COMMISSIONING PROCEDURES
Perform the following procedures for system commissioning.