Danfoss TTS300 - Soft Start Installation (Closed-Top)

Danfoss TTS300
294 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Figure 4-106 Open-Top Soft Start Connector Removal
5. RemovetheM5x20fastenersthatsecuretheSoftStartmountingbrackettothecompressor.Referto
Figure4-107Open-TopSoftStartRemoval.
Figure 4-107 Open-Top Soft Start Removal
6. RemovetheSoftStartassemblyandplaceitinasafelocation.
4.14.6 Soft Start Installation (Closed-Top)
1. PlacetheSoftStartovertheACBusBars(boardsideup)withthefantowardtheIGV.
2. InstallconnectorsJ1,J7,andJ8.
3. FliptheSoftStartoverandplaceintomountingposition.
4. Fingertightenthefastenersandthentorqueto5Nm(44in.lb.).RefertoFigure4-108Closed-Top-Soft
StartInstallationonpage122.
M-SV-001-EN Rev. H-1/23/2023 Page 121 of 294