3 Installation PROline Prosonic Flow 93 PROFIBUS-DP/-PA
40 Endress+Hauser
3.4 Post-installation check
Perform the following checks after installing the measuring device on the pipe:
Device condition and specifications Notes
Is the device damaged (visual inspection)?
Does the device correspond to specifications at the measuring point,
including process temperature, ambient temperature, measuring
range, etc.?
see Page 143 ff.
Installation Notes
Are the measuring point number and labeling correct (visual
inspection)?
Process environment / process conditions Notes
Are the inlet and outlet runs respected? see Page 15, 16
Is the measuring device protected against moisture and direct
sunlight?